Week Commencing dd/mm Tasks Notes
15/10 RESEARCH/PLANNING  
22/10 RESEARCH/PLANNING  
29/10 RESEARCH/PLANNING  
05/11 RESEARCH/PLANNING  
12/11 RESEARCH/PLANNING  
19/11 RESEARCH/PLANNING  
26/11 RESEARCH/PLANNING Design Main Site (ongoing)
03/12 Design Main Site 3/12 – design

4/12 – start prototype build

6/12 – have prototype site

7/12 – project sign off

10/12 Extra Research If needed at this stage
17/12 Research for fully functional site Knowledge of forms, dynamic web – streamlined design
24/12 Build Site 24/12 – home page

26/12 – about page

27/12 – contact form

28/12 – portfolio page

Contingency until 31/12

31/12 Research and design for 1 column static Come up with designs, themes, layouts, content
07/01 Build 07/01 – home page

08/01 – about page

09/01 – add page

10/01 – add page

Contingency until 14/01

14/01 Research and design for 2 column static Come up with designs, themes, layouts, content
21/01 Build 21/01 – home page

22/01 – about page

23/01 – add page

24/01 – add page

Contingency until 28/01

28/01 Research and design for 3 column static Come up with designs, themes, layouts, content
04/02 Build 04/02 – home page

05/02 – about page

06/02 – add page

07/02 – add page

Contingency until 11/02

11/02 Project Review

Planning

Research

Go over everything that’s been done so far, alter plans if necessary, prepare research for next stage of project, think about purchasing URL to make live online
18/02 Research and design 2 column dynamic Come up with designs, themes, layouts, content
25/02 Build 25/02 – home page

26/02 – about page

27/02 – contact form

28/02 – add page

04/03 Build Dynamic aspects – logon, contact etc.

Contingency until 11/03

11/03 Research and design 1 or 2 column dynamic Come up with designs, themes, layouts, content
18/03 Build 18/03 – home page

19/03 – about page

20/03 – contact form

21/03 – add page

25/03 Build Dynamic aspects – logon, contact etc.

Contingency until 01/04

01/04 Project overview

Project completion

01/04 – insert all components into one fully functional portfolio website,

01/04 – Make site live (if possible)

08/04 Extra build/fix time Amend broken aspects of the project
15/04 Extra build/fix time Amend and complete fixing of broken aspects of the project
22/04 Extra build/fix time 24/04 – make site live (or update)

26/04 – ASSIGNMENT DEADLINE

 